Monday 7 October 2013

Epic Update : SAIL

SAIL’s Burnpur-based IISCO Steel Plant’s (ISP) modernization & expansion work entailing an investment of Rs 16,000 crore would be completed by the end of this financial year pursuant to which the plant will produce 2.9 million tonnes of Hot Metal after completion. The major facilities include a New 7 metre tall Coke Oven Battery (COB); two Sinter Machines; a new Blast Furnace of 4060 m3 volume with Top Pressure Recovery Turbine; three 150 tonne Basic Oxygen Furnace Converters; two 6-strand Billet Casters and one 4-strand Beam Blank/ Bloom Caster; Universal Section Mill; Wire Rod & Bar Mill with necessary auxiliary and service facilities.